Wednesday, October 19, 2011

Striping the Parking Lot

Parking lot was striped including handincap signs

Replanting Kalanchoe's



Ramiro and Jose replanting kalanchoe's in the clubhouse area.



Painting Speedbumps



PAINTING NEW SPEED BUMPS AND ALL THE REST.


Thursday, October 6, 2011

10/6/11 POURING ASPHALT




CONSTRUCTION COMPANY STARTED POURING ASPHALT.




Wednesday, October 5, 2011

10/5/11 - Road Repairs




2nd day of Road Maintenance.


Tuesday, October 4, 2011

2ND SET (STREET REPAIRS)


THIS IS IN FRONT OF 120 MISSISSIPPI.


STREET REPAIRS









ROAD REPAIRS BEGAN TODAY.

THEY WILL BE DOING FROM THE

ENTRANCE TO 120 MISSISSIPPI.






Monday, October 3, 2011

GRILL TIRES



Bought a set of used tires for the grill. (Here are the before and after pictures.)



LAWN MOWER TIRES

The lawn mower tires were both replaced.

STREET CLEANING



Elsie and Sylvia cleaning streets after the concrete debris was moved.



PAINTING

Jose and Ramiro painting fire hydrants and resaca water faucets.